NW Beaver Drive Overlay

Project Description


NW Beaver Drive – Merle Hay Rd. to North Corporate Limits
HMA (Asphalt) mill and overlay project along NW Beaver Drive from Merle Hay Road to the North Corporate Limits (approximately 3.25 miles). Project will include median/splitter island in locations along with recreational trail.

Project Status


At the August 7 council meeting the project was awarded to Grimes Asphalt of Des Moines, Iowa.  Click here to view the letter sent out to residents notifying them of the update on the project.

A public meeting was held on Tuesday, March 7 from 6:30 to 8:00 pm inside the Johnston City Council chambers located at 6221 Merle Hay Road.  Click here to read a letter to neighbors.  This is the most recent PowerPoint presentation related to this project.

Estimated Cost


Estimated Cost as of 8/7/2017 is $4,325,764.00

Contractor


Grimes Asphalt & Paving

Estimated Project Timeline


Construction anticipated to begin late August and finish by mid to late November.

Engineer Design


Nicole Sungren, MSA Professional Services


Construction Administration


Amy Quartell, Foth Infrastructure

City Staff Project Contact
Matt Greiner, Public Works Director
515.278.0822
Email Matt Greiner